Hall Financial Group - Hall Winery

Hall Winery - Hall Financial Group, St. Helena, CA
Start Date:

November 2007

Completion Date:

Scheduled for 2010

Project Description: New winery complex and pursuing LEED certification. The project consists of multiple facilities, including industrial production, offices, visitor center, central plant etc., some of which are new and some of which are historic renovations. This is a phased project

Systems Commissioned: Systems: chilled waste, glycol chilled water, condenser water, heating hot water, glycol hot water, domestic hot water and radiant floor. Chilled beams, air handling units, variable air volume/hot water reheat terminal units, fan coil units, exhaust fans, photovoltaics and lighting controls

Commissioning Scope: Commissioning kickoff meeting and process plan. Facilitate documenting OPR, Review the AE's BOD documentation for compliance with the OPR. Provide commissioning specification section. Control logic and integration process. Perform site observations and meetings. Assist issue resolutions on an as needed basis. Maintain master issues log. Create system readiness forms. Provide working drafts of FPTs, monthly commissioning status reports and final commissioning report. Complete LEED documentation for LEED E&A prerequisite 1

KBA Role: Prime commissioning agent

KBA Project Manager: Ryan Hay, PE, LEED AP, ACG CxA

Project Reference: Larry Levey, President, Hall Financial Group, (972) 377-1125

Back to project experience page

Keithly Barber Associates
Burien Office
14237R Ambaum Blvd. SW
Burien, WA 98166

Ph: 206.835.8254
Fax: 206.246.1691

 

 

 

Keithly Barber Associates
San Francisco Office
332 Pine Street, Ste 307
San Francisco, CA 94104

Ph: 415.788.0211