Quest Stadium, Seattle WA

Qwest Field (Seahawks Stadium), Seattle, WA
Start Date:

2000

Completion Date:

2003

Project Description: New construction, 810K square foot (not including field and stands) professional football and soccer stadium including concessions, restaurant, suites, laundry, locker rooms and offices.

Project Scope: Full mechanical commissioning and partial electrical commissioning including large constant volume and variable speed air handlers, VAV terminals, water source heat pumps, packaged units, split systems, gas furnaces, exhaust fans, relief fans, Siemens controls and lighting control. Electrical systems commissioned included transformers and main switch gear. Detailed energy impact report relating to commissioned systems was issued in final commissioning report per Seattle City Light guidelines. The report outlined issues that were discovered through the commissioning process that directly relate to energy consumption, identified specific energy implications, and provided suggested energy savings measures. Estimated annual energy savings totaled 626,338 kWh.

KBA Role: Prime commissioning agent.

KBA Principal-in-Charge: Pete Keithly, CSI-CDT, LEED AP, CxA

Project Reference: Tom Chiado, (206) 550-8363

Back to project experience page

Keithly Barber Associates
Burien Office
14237R Ambaum Blvd. SW
Burien, WA 98166

Ph: 206.835.8254
Fax: 206.246.1691

 

 

 

Keithly Barber Associates
San Francisco Office
332 Pine Street, Ste 307
San Francisco, CA 94104

Ph: 415.788.0211