Alder Creek Middle School - Tahoe-Truckee Unified S.D
March 2003
November 2007
Project Description: New construction of 87,000 square foot two-story middle school. Demonstration project for the Collaborative for High Performance Schools (CHPS) program, done with support from the California Energy Commission.
KBA Scope: Full commissioning of HVAC system, DDC system and lighting controls including specifications, design review and intent, and sustainable materials and energy efficiency verification. HVAC system comprised of a ground source heat pump system with a back-up gas pulse combustion condensing boiler and VFD pumps as well as a water loop with gas boilers to pre-heat outside air. The HVAC system is controlled by a Honeywell DDC system. Lighting controls include occupancy sensors, photocell on/off daylighting controls and a low-voltage panel system for common area and exterior lights.
KBA Role: Prime commissioning agent
KBA Project Manager: Holly Townes, PE
Project Reference: Rob Koster, Project Manager, Facilities Department, Tahoe-Truckee Unified S.D., (530) 582-2542
Keithly Barber Associates
Burien Office
14237R Ambaum Blvd. SW
Burien, WA 98166
Ph: 206.835.8254
Fax: 206.246.1691
Keithly Barber Associates
San Francisco Office
332 Pine Street, Ste 307
San Francisco, CA 94104
Ph: 415.788.0211